The news area provides information updates on the AGL Bluff Wind Farm Project. Copies of newsletters and other PR material can be downloaded here.

Newsletters

We will post electronic copies of our community newsletters and other PR material here. Please check back later for updates.

Latest News
Aboriginal Awareness Workshop - May 2011
Media Release - February 2010: AGL to Construct Hallett 5 Wind Farm to Meet Renewable Energy Supply Contracts
Media Release - July 2010: Hallett Wind Farm Projects Boost Local Economy
Media Release - August 2010: AGL Announces 2010 Community Funding Round
Media Release - Clean Energy Council: Experts Silence Wind Farm Noise
Visit the AGL Blog
Latest Transport Information
From 17th January 2011 until 27th May 2011, large wind turbine components will be delivered to site. This includes tower sections, blades and nacelles. All of these components will require police escort due to their size and weight. We understand that this may cause inconvenience to local road users on occasions and we apologise for this.

The transport contractor and police will endeavour to minimise impact on other road users by allowing traffic to pass at regular intervals.

A monthly update will be provided to ensure that the latest information is available. By reviewing the information, travellers may be able to avoid using the roads when these deliveries are being made.

The longest loads are the blades at 44m and the heaviest load is the nacelles at 80 Tonnes.

March 2011
One blade delivery is expected on each of the 2nd, 4th, 7th, 11th, 16th, 18th, 21st, 23rd, 25th, 28th and 30th March.
No tower section deliveries are expected in March.
Nacelle deliveries are expected on 2nd, 4th, 7th, 9th, 11th, 16th, 18th, 21st, 23rd, 25th, 28th and 30th March.

April 2011
No blade deliveries are expected in April.
One tower section delivery is expected from Portland on the 29th April.
No tower sections are expected in April from Kilburn.
Nacelle deliveries are expected on 1st, 5th and the 7th April..
Refer to local map for routes from Adelaide and Portland to site.

May 2011
No blade deliveries are expected in May.
Tower section deliveries are expected from Portland on the 3rd, 6th, 10th, 13th, 17th, 20th, 24th and 27th May.
No tower sections are expected from Kilburn in May.
No nacelle deliveries are expected in May.
Refer to local map for routes from Adelaide and Portland to site.

Spotlight On...

Steve Martin

Steve Martin

Site Manager,
Bluff Wind Farm.

Read more »